Sprint 8 Task Status — Week 2
Updated: April 2, 2026

TASK-801: API rate limiting implementation
  Assignee: Sarah Chen
  Progress: 75%
  Status: in_progress
  Estimated completion: by next Tuesday

TASK-802: User dashboard redesign
  Assignee: Mike Torres
  Progress: 100%
  Status: completed

TASK-803: Database index optimization
  Assignee: Alex Zhang
  Progress: 40%
  Status: in_progress
  Estimated completion: end of next week

TASK-804: CI/CD pipeline upgrade
  Assignee: Jordan Lee
  Progress: 60%
  Status: in_progress
  Estimated completion: April 10

TASK-805: Security audit fixes
  Assignee: Sarah Chen
  Progress: 90%
  Status: in_progress
  Estimated completion: tomorrow